Visit of the French Ambassador at Rokkasho on 12/11/2018

On November 12th, 2018, we were honored by the visit of the French Ambassador, his excellency Laurent Pic, and his delegation at Rokkasho. We were given the chance to present the activities performed at the IFERC site…

… followed by a tour focusing on the LIPAc activities. It was explained that these activities are conducted in the frame of the Broader Approach Agreement and the IFMIF/EVEDA Project. Emphasis was given to the substantial contribution from the French institute CEA being a key part of the European contribution.

The “Francophone” working at Rokkasho were given the opportunity to share their experience about living in the north of Japan and working in this international partnership.

The ambassador was favourably impressed by the activities ongoing at Rokkasho under the European – Japanese collaboration and confirmed the strong interest of France in this project.

Before leaving, he promised that he will come back soon to learn more about the progress in the commissioning of the accelerator systems.

Project Committee #22    

15 & 16 October 2018

The 22nd Project Committee was held at Rokkasho IFERC Site on October 15th and 16th, during which an update of the project was presented as well as the outlook from 2019 onward.

The main topics discussed were the progress since the last PC#21 with the first Beam Operation, the imminent resuming of the beam operation throught the RFQ and the preparation for the phase C with the delivery of the High Energy Beam Transport line and its Beam Dump as well as the assembly of the Cryomodule in the clean room at Rokkasho.

Attendees PC#22

The PC members in the LIPAc Control Room

LIPAc operation broadcast LIVE online

On 27 July 2018, from 4pm JST (9am CEST) a special broadcasting took place from LIPAc’s control room, with explanations, interviews to the LIPAc Operation Team staff about the different subsystems and the operational aspects. The engineers from Europe were also interviewed and presented their own institutes and expectations for the future.

http://live.nicovideo.jp/gate/lv314610330

Phase B configuration (stage at 5 MeV with deuterons and 2.5 MeV with protons)

1st Workshop on Advanced Neutron Sources and their applications

4-5 November, 2017
Aomori-city, Japan

Saturday, 4 November 2017 (@IFERC site and Festival city Auga)

8:30 Departing from Nebuta museum “WA RASSE”nearby Hotel Route Inn Aomori Station
10:00 Arriving at the IFERC Site and tour to LIPAc
12:00 Departing the IFERC Site (Light meal will be provided at the site for lunch)
13:30 Arriving at Auga
14:00 Opening (A. Ibarra, S. O’hira)
14:15 Technical Session 1:  Users’ perspective on neutron sources for materials development:T. Muroga (NIFS)
15:00 Technical Session 2-1: Presentations about the neutron sources developed or being developed

Chair: Shigeru O’hira (QST)  (30 +10 min x 4 presentations)

  – DONES: DEMO-Oriented Neutron Source: A. Ibarra (CIEMAT)
  – Advanced-Fusion Neutron Source: K. Ochiai (QST)
  –Multi-Aimed Intense Neutron Source (MAINS) based on BISOL: Y. Wang  (Peking Univ.)
  – Neutron sources for transmutation of long-lived fission products: H. Okuno (Riken)
 18:00 Adjourn

 

Sunday, 5 November 2017 (@Link-Station Aomori)

9:30 Technical Session 2-2:  Presentations about the neutron sources developed or being developed (30 min x 3 presentations + discussion).

Chair: Juan Knaster (IFMIF/EVEDA)

  – Neutron sources for transmutation applications (including MYRRHA): D. Terentiev, (SCK-CEN)
  – D-T neutron sources (including HINEG, SORGENTINA, etc): Y. Wu (FDS)
11:30  Lunch
12:45 Technical Session 3:  Panel Discussion on development of neutron sources.

Chair: Angel Ibarra (CIEMAT); High/Low power neutron sources (4-5 items, 10-15 min. each + discussion)

Accelerator-related issues. Promoter: Juan Knaster (IFMIF/EVEDA)
  – Comparison of a few schemes of RFQ-based compact neutron sources: S. Kurokawa (KEK)
  – High power linacs: J. Knaster (IFMIF/EVEDA)
Target-related Promoter: K. Ochiai (QST)
  – Design and technical challenges of Li target for IFMIF-based neutron sources: D. Bernardi (ENEA)
  – Target challenge for High power compact accelerator based neutron source; as status of the iBNCT: the heat issue and blistering: T. Kurihara (KEK)
  – Present status of neutron target on J-parc Presentaer: T. Naoe (JAEA/J-parc)
Irradiation area- related issues. Promoter: F. Arbeiter (KIT) (4-5 items, 10-15 min. each + discussion)
Complementary Experiments at DONES: W. Królas, A. Ibarra, A. Maj, F. Arbeiter
Comment on the middle flux module: T. Nishitani (NIFS)
Tools and procedures for radiation damage modelling and intercomparison of experiments:

F. Mota, C. J. Ortiz, R. Vila (CIEMAT)

 16:30 Technical Session 4: Summary session   Chair: K. Ochiai (QST)
  – From IFMIF users committee: IEA/W-GIFT history and proposal (15 min.): E. Diegele (EUROfusione)
  – Summary: J. Knaster (IFMIF/EVEDA)
 17:30 Adjourn

 

European Research Day 2016

The European Research Day 2016 (ERD) took place on 25 November 2016 in Tokyo.

It is a one-day workshop featuring presentations by European researchers, discussion panels

on issues of relevance for Japan-Europe mobility and research cooperation, and a networking reception.

Francesco gave a superb presentation on his research for the IFMIF project.

IMG-20161125-WA0036

10th LIPAc Technical Meeting (LTM10)

LTM10_Group_Photo_
LTM10 – Participants, Rokkasho Japan

 

The tenth LIPAc Technical Meeting 10 (LTM10) was held in Rokkasho (Japan) from November 14th until 17th, where the current status of the design, manufacturing, installation and commissioning of the LIPAc accelerator’s components were discussed. More than 30 experts from laboratories in Europe, including CIEMAT (Madrid, Spain), CEA (Saclay, France) INFN (Legnaro, Italy); and Japan, including QST (Rokkasho, Japan) and KEK (on behalf of QST) attended the meeting, which was coordinated by the LIPAc Project Team and QST. In addition, videoconferencing was available to allow remote participation of EU colleagues who could not attend in person.

Detailed discussions were held to reach common agreement on the key technical issues that have arisen, and progress was reported on many aspects of the project. The following gives an overview of the progress made in key areas:

Injector:

Full commencement of phase “B” commissioning was announced, and the LEBT (Low Energy Beam Transport) was removed to allow final positioning of the RFQ. During the last campaign of Injector commissioning, a current of 112 mA with acceptable emittance in CW operation was achieved. While this falls short of the goal, this represents an excellent improvement. Further adjustments must be made to the accelerator column, followed by 24/7 beam extraction, to achieve the target parameters.

DSC05317
Injector configuration without LEBT, and RFQ (right) in its final position

 

RFQ:

The bead pull measurements were successfully completed, and the final measured frequency was equal to 174.089 MHz. When scaled to the normal operating temperature of 20 °C and considering the effects of vacuum and beam loading, this is equivalent to 175.014 MHz. Following LEBT removal, the RFQ super modules were placed in their final position, and aligned within a tolerance of 50 µm. The RFQ was pumped down and the correct vacuum conditions for the three super-modules were achieved. The RFQ can now be baked-out before final assembly can proceed. Control cubicles and junction boxes were installed and are now being configured.

DSC05314
RFQ in final position

RF System and Coaxial lines:

Tangible progress was made since LTM09, which was held in April 2016. RF module 02 for the SRF LINAc was tested and sent to Saclay for Sathori test stand. After use in Saclay, it will be sent to Rokkasho for installation in Rokkasho. RF module 03 will be sent to Rokkasho on 30th of November 2016, together with the SRF LINAc coaxial lines, while RF module 04 is now in the final stages of preparation at Indra’s facilities, and is expected to be ready for shipment to Rokkasho in January 2017. The installation of the RF cooling system onsite is almost complete. The RFQ coaxial lines have been installed in preliminary position. Final positioning will be made after the connection is made to the RFQ.

DSC05305
RF System view

MEBT and D-Plate:

Most of the installation and commissioning activities of the MEBT and D-plate were performed in parallel during pre-commissioning last summer 2016. Preparation for the next installation campaign already started with the objective to reach the LIPAc phase B configuration (Injector-RFQ-MEBT-Dplate and LPBD) next year. The displacement of the MEBT to its final position is planned beginning of 2017. Once it is validated by an alignment survey, it will be followed by displacement and alignment of the Dplate. Then the ancillaries (cabling, piping, compressed air and vacuum) will be installed on both equipment and tested. The integration of LCD into CCS will conclude this campaign; at least for these two accelerator components, driving to their check out and commissioning.

DSC05174
MEBT & D-plate in their temporary positions

SRF Linac and Cleanroom:

All the main components of the cryomodule are expected at CEA (Saclay, France) by the end of March 2017 and ready for shipment to Rokkasho by the end of April 2016. It was agreed that the assembly of the cryomodule will be performed at Rokkasho in dedicated clean room which will be available in Rokkasho by the end October 2017.

The Sathori test stand is prepared and awaiting commissioning of the power supplies and RF modules. CEA expect to start testing the cavities at the beginning of 2017

Cryoplant:

Most of the components for the cryoplant have been delivered to Rokkasho. The final components, including the helium buffer tank and the control cubicles, will be delivered during December 2016. The installation activities started during November, with the first major components being installed in their final locations and the commencement of piping works. Civil work associated with the cryoplant is also progressing with the construction of the foundations for the Nitrogen and Helium storage tanks.

DSC05321
Shelter view (inside) – Helium compressor (yellow) and Oil Removal System (ORS)

HEBT/BD:

The HEBT manufacturing drawings have been completed and many components, such as the water cooling system, and associated pipe, fittings and valves; have been manufactured or procured and delivered to Rokkasho. 4 out of 5 HEBT support frames have been manufactured at CIEMAT, and manufacturing of the first quadrupole is complete. For the beam dump, the inner cone of the first prototype has been manufactured, and a second prototype is being manufactured. The acceptance tests for the beam dump shield are expected to proceed at CIEMAT in December 2016. The main steel shielding and mobile shielding manufacture is now in an advanced state, and final acceptance tests are expected in February 2017. The cooling system design continues, but manufacture will need to be accelerated to match with the current schedule.

HEBT (2)
Beam Dump – 3DMock-up

 

HEBT (1)
HEBT 3DMock-up

Control system:

Phase B commissioning is approaching, and as such, the dedicated control configuration is required for the control system. An additional 42 signals are required, a test bench for the timing system has been prepared, and the program for data creation is being prepared. Local control system integration for phase B will include the RFQ, RF/LLRF, MEBT and D-plate. The Central Control System upgrade contract is expected to start in January 2017. Moreover the need for a beam simulation study to optimize the configuration of beam was recognized as being urgent. Data event recording tool must be implemented, and the operational screens in the control room are being prepared according to the needs of the different subsystems.

 

The next meeting LTM11 will be held between April and May 2017, with the location yet to be decided.  

 

 

 

 

Celebrating major milestones of the Linear IFMIF Prototype Accelerator (LIPAc) in Rokkasho

On Thursday 21 April, a celebration took place as major accelerator components had been transported by F4E to the Rokkasho Fusion Centre allowing the start of second phase in the commissioning of LIPAc. This is another major milestone on road of success for the IFMIF/EVEDA Project. Already in 2013, the engineering design activities were successfully accomplished on schedule. By 2015, the Target and Test facility validation activities were fully completed, with the exception of the on-going corrosion/erosion tests in the lithium loop constructed in Brasimone by ENEA. This facility is now providing important results to quantify the corrosion/erosion rates of fusion reactor steel grades in contact with a high speed flow of liquid lithium.

LIPAcNew
LIPAc accelerator and breackdown of contributions

The LIPAc is under installation and commissioning in Rokkasho. Its key systems are designed and manufactured mainly by CEA, CIEMAT and INFN integrating also some important components contributed by SCK-CEN (see Figure above for a breakdown of the contributions). The LIPAc is designated to operate in unprecedented beam conditions at the cutting edge of present days’ accelerators technologies. During the previous meeting of Broader Approach Steering Committee (BASC-17), hosted on 11 December 2015 by RFX, an extension of the LIPAc validation period until December 2019 was approved. The deuteron source (Injector) developed by CEA has demonstrated that the beam characteristics are achievable in a parameter field never reached before (100 kA and 140 mA deuteron beam). An operational point with protons to be used as beam input to the ensuing accelerator stage, the Radio Frequency Quadrupole (RFQ) developed by INFN, has been determined. Additional commissioning of the Injector towards the mandated operation mode in Continuous Wave, i.e. 100% duty cycle of the beam, will take place during 2016 interleaved with the preparation activities for beam commissioning with the RFQ. The RFQ now under installation at Rokkasho is the longest one ever constructed. Today 6 out of 8 RF power chains developed by CIEMAT are already installed, which are to deliver 200 kW each to operate the RFQ. The last two chains are to arrive before the summer.

 Ceremony2p  Ceremony3p

The celebration of the success of the Injector commissioning and the start of installation of the RFQ and the RF power generator for the Linear IFMIF Prototype Accelerator enjoyed utmost interest among European and Japanese partners. The celebration received the participation of representation from the European Delegation in Japan and the Embassies of all the six European countries that have been involved in the IFMIF/EVEDA project. Among the European guests were the Ambassador of Spain to Japan, Gonzalo de Benito; the Director of Nuclear Energy, Safety and ITER of the DG Energy in the European Commission, Massimo Garribba; the Chairman of the Governing Board of F4E, Joaquin Sanchez; the Chairman of CEA, Daniel Verwaerde, the member of the Executive Board of INFN, Eugenio Nappi; the Directors of INFN Legnaro, Giovanni Fiorentini, and of INFN Torino, Amedeo Staiano; Angel Ibarra from CIEMAT. Among the Japanese guests were the Governor of Aomori Prefecture, Shingo Mimura; the President of QST, Toshio Hirano; the President of JAEA (to which the Japanese Fusion programme belong to until 31 March 2016), Toshio Kodama; the Deputy Director General of Research and Development Bureau at MEXT; Shuichiro Itakura.

   RFQlong1_Apr16     RFQlong2_Apr16

9th LIPAc Technical Meeting

LTM09 – Participants, Rokkasho Japan (Group photo)

 

The 9th LIPAc Technical Meeting (LTM09) was held at the IFERC Site in Rokkasho, Japan, from 19th to 22nd April 2016. More than 40 experts from different involved institutes, including CEA (Saclay, France), INFN (Legnaro, Italy), QST (Rokkasho, Japan), CIEMAT (Madrid, Spain), F4E (Garching, Germany) and the IFMIF/EVEDA Project Team; attended the meeting. In addition, Japanese experts from KEK and J-PARC attended on behalf of QST.

Many satellite meetings were held, with devoted discussions on most of the accelerator systems, including the MEBT (Medium Energy Beam Transport), HEBT (High Energy Beam Transport) and the Beam Dump; the control systems, including vacuum system integration and its overall process management, the control room configuration; the different phases of LIPAc commissioning, including integrated operation scenarios and beam dynamics issues; and the cryomodule assembly.
During the LTM, much detailed technical information was presented, highlighting the significant progress that has been made for the manufacture and installation of various components since the previous LTM08 held in Garching (Germany) on 24-26 November 2015.

 

LIPAc Components Overview, Injector-RFQ-MEBT and D-plate

The main outcomes presented during the meeting are listed below:

• Injector
Over the last 6 months injector operations have been very intense: 3 measurements campaigns were carried out as well as curative and major preventive maintenance. The deuteron beam commissioning performed in December 2015 gave promising results, the emittance met specifications at 20  % and 50 % duty cycle for currents of 110 mA at the level of the beam stop. In March 2016, the measurement campaign with a proton beam, which is a scaled version by a factor of 0.5 in intensity and energy, but with the same perveance as a deuteron beam, enabled to find a good working point at 10 % duty cycle. The last measurement campaign was very effective thanks to the careful maintenance performed and to Tracewin simulations which made it possible to determine the most interesting sets of machine parameters giving the best beam characteristic

RF power area – RF chain for RFQ system and its cable trays for cables installation

 

  • RF power systems

Remarkable progress was made for the RF system, with the delivery and installation inside RF power supply area of the Accelerator Building of all of the HVPSs and the first three RF Modules for the RFQ. The main cable trays, panel boards and grounding systems have also been installed, and the transformers and the HV breakers on the electrical platform are complete.

The four RF modules for the SRF LINAc have been manufactured, and the first unit has been partially tested and will soon be ready for shipment. It will be shipped to CEA Saclay for integration on the Sathori Test Stand.

  • RFQ

The RFQ super module installation was successfully completed according to the schedule presented at LTM08 (Garching, Germany). The bead pull measurements will commence on 25/04/16 and will be completed by the end of July after 3 campaigns of measurement. The RFQ will then be relocated to its final position immediately afterwards.

The RFQ cooling skid and accessories are at Rokkasho and the water cooling skid requires some adjustment before its final installation/site commissioning.

LIPAc’s team members, during RFQ installation, April 2016 (Group photo)

  • MEBT

The MEBT arrived in Rokkasho in March 2016, and was temporarily positioned inside the Accelerator Vault by the end of March. The electrical cubicles and other electrical equipment are expected to arrive in the middle of July, while the cooling skid, piping and associated accessories are currently being manufactured

  • D-Plate

The D-plate was installed inside the Accelerator Vault in a temporary position, in April 2016.

MEBT_D-plate_r
MEBT and D-plate, temporarily positioned inside the LIPAc vault

  • SRF Linac

While licensing activities for the complete cryomodule continue, the formal approval of the cavity design by KHK was obtained representing a great success for those involved.

Manufacturing contracts for all critical components have now been placed, and the tender process for a number of non-critical-path items has also been launched. Agreement has nearly been reached on the definition of the requirements for the clean room to be constructed at Rokkasho, and the tendering process for the clean room’s construction is expected to start by June.

  • Cryoplant

The main cryogenic system components, including He compressors, oil removal system and cold box, have been manufactured and delivered to Rokkasho.

The requirements for the licensing of the cryoplant have been clarified. The cryoplant distribution piping and equipment are currently being designed.

  • HEBT/Beam Dump

The HEBT water cooling skid, which will cool the magnet of the MEBT and HEBT, arrived in Rokkasho in January 2016. It was positioned inside the Accelerator HEX room and the piping is expected to start after the final positioning of the MEBT, which will intervene after the final positioning and back out of the RFQ.

A number of manufacturing contracts for the HEBT are ongoing, including the construction of the quadrupole and dipole. The design of the beam chambers is complete and the technical specifications have been prepared. The remaining components, i.e., power supply, supports, magnets coil system, vacuum pumps and associated equipment; have also been designed and are being procured.

Design for manufacture continues for both the Beam Dump low alloy steel shielding and mobile shielding, with manufacturing expected to start for both at the end of May 2016. Final assembly and acceptance tests are expected to commence in September. Manufacturing is progressing well for the Beam Dump cartridge.

  • Control system

The dedicated Control Systems and LIPAc Operation satellite meeting was fruitful. It was identified that the integration of the different LCS into the CCS is on the critical path and mitigation actions should be considered. It was agreed also the need to tackle the various operational issues e.g. setup of the vacuum systems, identifying the thresholds for the MPS and setup of common operating procedures. An operating procedure for phase B, including a start-up procedure needs to be prepared urgently and missing operations with possible proposed configurations must be identified.

The meeting was successful in spite the overlapping of Broader Approach Steering Committee half-yearly meeting (BASC) and LIPAc ceremony. The main actors who have done all the technical work could also attend LIPAc ceremony and finally to the pleasant banquet that took place in the Kizan restaurant in Misawa, together with all ceremony participants for the celebration of success of the Injector commissioning and the start of installation of the RFQ and RF power generation for the LIPAc.

See you at the next LTM10 at the end of November 2016, again in Rokkasho (Japan)

7th LIPAc Technical Meeting

Group picture LTM07
LTM07 – Participants, Rokkasho – Japan (Group picture)

   

The 7th LIPAc Technical Meeting (LTM07) was held at Rokkasho, BA site Fusion Research Center (Japan) from 15th to 17th June 2015, and on the following two days Satellite meetings with more detailed technical discussions were held.

More than 40 experts from CEA (Saclay, France), INFN (Legnaro, Italy), JAEA (Rokkasho, Japan), CIEMAT (Madrid, Spain), F4E (Garching, Germany)and the IFMIF/EVEDA Project Team attended the meeting with additional European experts contributing remotely by videoconference.

Attendees LTM07 (partial view)
Partial view of the attendees LTM07

 

The technical information that was presented at the meeting highlighted the significant progress achieved for the various components since the last LTM06 in November 2014.

A particular highlight was the positive results that are presently obtained from the Injector commissioning as shown by the operation leader, Yoshikazu Okumura.

 

 

 

The main outcomes presented during this meeting are listed below:

Injector

Injector commissioning
Injector commissioning phase A1.2, Emittance measurement

The Injector commissioning resumed on April 22nd with the objective to complete the phase A1.2 (H+ beam, energy 50keV,variation d.c.,UIE,Itot) including the characterization and optimization of the proton beam. Performances of 100kV/155mA @ 20% duty cycle were reached during this campaign, allowing optimization of the beam emittance. Continuous wave (CW) operation was also tested successfully at 120 mA/100 kVeV, with 650 W RF power and SCCM gas flow rate.

The next important step is expected in July with the proposed start of deuterium operation (phase A1.3) after the Facility inspection by Radiation Authority.

 

 

 

Electrical platform
LIPAc Electrical platform

RF power systems

Installation of transformers and the HV breakers on the electrical platform has started with JAEA contractor NKK. The contract for the remaining cable trays will be launched soon.

The delivery of the HVPS and RF power system for the RFQ is expected by the end of July 2015 at Rokkasho and its installation will take place upon its arrival.

 

 

 

 

 

  • The RFQ super modules are nearing completion at INFN Legnaro (Italy) and will be shipped in December 2015 after the final acceptance test at Legnaro in November 2015. Cooling skid, piping and accessories will be shipped by the end of September 2015. The remaining components will be shipped to Rokkasho by February 2016.
  • MEBT: much work has been completed in the last months to finish the manufacturing and the tests of the main components and auxiliaries. CIEMAT continue to push to have the beamline integrated for test by the end of this summer, with the aim to have the MEBT delivered to Rokkasho at the beginning of 2016.
  • The LPBD detailed design is on going, was showed in the presentation its readiness for construction. Details for its cooling system were also discussed during the LTM.
  • The SRF Linac design is completed and manufacturing contracts for the critical components have been placed. The licensing activities are on-going.
  • The D-Plate is almost completed and will be ready for shipment by November 2014. Some activities of alignment of the components need to be confirmed by ensuring the reproducibility of the ideal accuracy expected.
  • The HEBT and Beam Dump main components designs partially completed as already discussed in the previous LTM06 held last November 2015. Technical specifications are nearing completion and several manufacturing contracts have been launched
  • Writing of the beam dump cooling system specification will start soon

Controlarea PPS
Control room PPS, main control console with monitors

 

  • PPS-MPS,are now operational for injector commissioning. However, some modifications will be necessary for the next phase, especially with respect to the integration into the CCS, which is considered as an important milestone;

 

 

A site visit of the Accelerator Prototype Building was held, giving all attendees the opportunity to visit the vault and the RF area.

 

Dinner
LTM07 attendees at Japanese restaurant “Darumaya”

Hirosaki
Cherry blossom, Hirosaki (Japan)

 

 

 

 

 

 

 

 

 

A pleasant event on the second day of the meetings was organized in a typical Japanese Restaurant in Rokkasho called “Darumaya”.

See you next LTM08 in Garching!

LTM08 will be held on Tuesday 24th, Wednesday 25th and Thursday 26th of November 2015.