Project Committee #24

15 & 16 October 2019

The 24th Project Committee (PC#24) was held at Rokkasho Broader Approach Site on October 15 and 16. The project status and achievements were presented as well as the outlook from phase B+ onward. The main update topics discussed were:

  • RF system improvement
  • Phase B milestone beam perveance record
  • Beam Dump installation resumed
  • Phase B end and the maintenance period start
  • Technical difficulties
  • Next objectives towards continuous wave operation
  • Objectives of High Energy Beam Transport line and Beam Dump validation
  • Long-term improvement actions
  • Preparation of the Medium Energy Beam Transport extension line
  • Status of superconducting solenoids procurement for the SRF Linac Cryomodule
  • Preparatory status for the clean room assembly of the Cryomodule

The action plan for 2020 was presented for installation, maintenance and operation.

Attendees PC#24

LIPAc maintenance period and High Energy beam line installation

25 September 2019

After the completion of operation corresponding to the phase B, the maintenance activities have started mid of August as planned alongside the preparation of the next phase: phase B+. In this long maintenance period, it is important to carry-out both the curative maintenance of components that were malfunctioning and the preventive maintenance to ensure a better reliability and availability of the systems for the next operation campaigns. The maintenance activities are planned targeting to resume Injector continuous wave operation and Radio-Frequency Quadrupole (RFQ) conditioning before end of 2019, so that LIPAc operation can restart in the second quarter of 2020. In this first period higher priority has therefore been assigned to the Injector and RF/RFQ systems maintenance.

LIPAc configuration in phase B+

Maintenance activities of the Diagnostics-Plate and of the vacuum systems have also started; maintenance of the Medium-Energy Beam Transport line (MEBT) are planned in December. Specific activities on the beam instrumentation will be carried out in November with EU experts from CEA and INFN on-site. The final beam instrumentation checkout will take place after the installation of the MEBT extension line.

3-dimensional view of the MEBT extension line for phase B+

The maintenance of the ancillaries is on-going and many activities have already been completed, such as electrical network distribution, secondary cooling system, Personnel Protection System, Accelerator vault crane. The cryoplant maintenance activities will be carried out in the first quarter of 2020.

The upgrade of LIPAc into its future phase B+ configuration, with its High Energy Beam Transport line (HEBT), is also the goal of this maintenance period. The MEBT extension line has been designed to transport the beam at 5 MeV instead of the cryomodule. It is composed of quadrupoles to focus the beam, steerers to correct its trajectory, Beam Position Monitors to monitor the beam orbit, a vacuum chamber to host a Residual Gas Bunch Length Monitor, Beam Loss Monitors and turbo-pumps for vacuum pumping. The components of the MEBT extension line are currently being procured or manufactured.

Alignment and connection work for HEBT

The Low Power Beam Dump which was used during phases A and B will be removed. The HEBT is positioned in its final position together with the Diagnostics Plate, and the LIPAc Beam Dump for full beam energy will be connected to the beam line.

Successful acceleration of a 125 mA deuteron beam @5 MeV in LIPAc!!!

24 July 2019

The deuteron (D+) beam commissioning has been ongoing since two months, and we achieved a 125 mA beam acceleration by the Radio Frequency Quadrupole (RFQ), and transported to the Low Power Beam Dump (LPBD) on the 24th of July, 2019. The data was obtained in pulsed mode operation of ion plasma source with 1 ms length and 1 Hz repetition rate.

D+ Beam measurement along the LIPAc

The beam current range was varying from 50 to 140 mA at the entrance of RFQ, and 90% transmission through the RFQ was measured for a maximum current of 125 mA (measurement taken at the end of the beam pulse shape) and for a rated RFQ cavity voltage of 132 kV.

D+ Beam characteristics

The detail of the accelerated beam characteristics is under investigation and the commissioning phase is still ongoing.

This significant outcome demonstrates that all the components of the LIPAc accelerator in the phase B configuration meet the design requirements. This achievement gives us confidence for the future and the next step toward continuous wave operation at 5 MeV with its high energy beam transport line.

Status Proton Beam Commissioning @2.5 MeV (Phase B1)

25 May 2019

The proton characterization at 2.5 MeV was completed on April 30, 2019 (Phase B1). During this phase, with an extracted current of 88 mA and 300 µs maximum pulse length from the injector, a maximum current of 57 mA was accelerated in the Radio Frequency Quadrupole (RFQ) with a transmission of 93 % through RFQ and beam transport line up to the Low Power Beam Dump (LPBD).

Summary of Phase B1 commissioning

The RFQ was conditioned for proton level operation, which requires a field of about 70 kV to accelerate the protons. In the case of the deuteron operation (next phase B2, and nominal condition of the machine), the cavity needs to be conditioned to reach a maximum field of 142 kV. The conditioning is still on-going to reach that field level with pulses up to 300 µs.

The Beam Instrumentation has also demonstrated to be operational. Further improvements are ongoing which should ease beam operation and allow data analysis with comparison to beam dynamics models.

SLIT (Ciemat)/ SEM GRID (CEA) Interceptive diagnostic measurement

As an example, the above figure on the left shows the measurement of beam profiles, providing the shape of the beam. On the right, the beam position in space is monitored.

F4E News

Beam operations resume at LIPAc

Project Committee #23

18 & 19 March 2019

The 23nd Project Committee (PC#23) was held at Rokkasho IFERC Site on March 18th and 19th, during which an update of the project status was presented as well as the outlook from 2019 onward.

The main topics discussed were the progress since the last PC#22 with the achievement of the annual maintenance campaign, the completion the HEBT and Beam Dump installation in the accelerator line and the resumption of the Beam Operation with proton beam and the first deuteron injection into the RFQ. The preparatory work for the assembly of the Cryomodule in the clean room at Rokkasho was also presented.

Attendees PC#23

The PC members in the LIPAc Control Room participating to the beam operation

LIPAc News

3 weeks after resuming the operation….

The maintenance period was completed early 2019 and the acceleration of proton beams up to 2.5 MeV was resumed on 20 February. A transmission of 95% through the RFQ was achieved with an input beam current of 7 mA and 0.3 ms pulse length. By using such a beam, the phase tuning of the two bunchers installed in the MEBT was performed successfully. The basic beam diagnostics, beam current monitors (ACCT) and beam position monitors (BPM), were used regularly for beam commissioning, and the beam profile measurement was started by using a non-interceptive device (Fluorescence Profile Monitors) and an interceptive one (Secondary electron emission grid monitors). The latter one is also used to measure the beam emittance with a slit insertion.

1 ms Proton beam pulse measure at the entrance and output of the RFQ during emittance measurement (no signal on DPlate and LPBD due to the insertion of the slit for emittance measurement)

F4E News

IFMIF/EVEDA – Engineering and validation of equipment in progress

First LIPAc Commissioning and Beam Operation Workshop at Rokkasho!!!

After completing the first beam operation stage, and while profiting ofthe stop of the machine for the scheduled maintenance, the first LIPAcCommissioning and Beam Operation workshop was organized at Rokkasho site. [read more]

Visit of the French Ambassador at Rokkasho on 12/11/2018

On November 12th, 2018, we were honored by the visit of the French Ambassador, his excellency Laurent Pic, and his delegation at Rokkasho. We were given the chance to present the activities performed at the IFERC site [read more]

Project Committee #22

The 22nd Project Committee was held at Rokkasho IFERC Site on October 15th and 16th, during which an update of the project was presented as well as the outlook from 2019 onward [read more]

 

Transfer of Ownership between F4E and QST

On October 16th, 2018 the transfer of ownership of Beam Instrumentation, Medium Energy Beam Transport and  Radio Frequency Quadrupole [read more]

F4E News

Europe and Japan operate accelerator to deliver first beam

First proton beam injected into the RFQ on 13 June 2018!!!

As a major milestone towards the validation of the IFMIF accelerator design, the first beam has been injected into the RFQ at the LIPAc (Linear IFMIF Prototype Accelerator) at Rokkasho on 13 June 2018.

After some optimization, on Friday 15 June 2018 more than 80% of transmission in the RFQ was achieved.

This first campaign consisting of the full characterization of the proton beam at low duty cycle, followed by an increase of the beam current up to 65mA, will last almost 8 weeks, and will be followed by the deuteron beam operation. Besides this important milestone being reached, LIPAc project will have to face other important challenges before the start of the next phase with the assembly of the SRF Linac at Rokkasho site and the installation of the HEBT/BD required to reach the final targeted 9MeV.

Congratulations to the LIPAc Operation Team!!

The international team of European and Japanese scientists and engineers celebrating this important milestone

Further check the dedicated newsline.